Inferno in the Caspian Regaining control of a 30-well production platform

Foreman, Mike Paulsen, Will Munoz, Miguel

Inferno in the Caspian Regaining control of a 30-well production platform - ene. 2017 - 4 p. ; 27-31

Hurricane force winds led to a multi-well fire on a 30-well production platform. In spite of continuing adverse conditions, well control specialists were able to safely extinguish the blaze in 64 days, 25 of which were non-productive due to the weather.